Project 20

48 Assembly Drive – WH1A

Location
Dandenong
Status
In Progress
Category
Industrial
Builder
2Construct
CLient
Alirro & General Motors

Scope of Works

48 Assembly Drive, WH1A, Dandenong involved converting a single-user site into a multi-tenant operation, requiring both infrastructure expansion and complete reconfiguration to support multiple occupants, with all design completed in-house by the JMP team.

Electrical scope:

  • Consumer mains, sub-mains and switchboard infrastructure installed to support the site's new multi-tenant configuration
  • Replacement of existing switchboards to accommodate the reconfigured supply arrangement
  • Lighting installation across the reconfigured tenancies
  • Reconfiguration of services across tenancies, dividing what was previously a single-user supply into separately metered, independently serviced tenancies
  • Civil works and site services infrastructure supporting the broader redevelopment
  • Mechanical services, dock levellers and EV charging installed as part of the site upgrade
  • Energy Management System installed and aligned to Green Star requirements, supporting the site's long-term sustainability performance

A key challenge was delivering the works while the WH1A side of the site remained tenanted and fully operational. This required a high level of coordination and project management, close client liaison to maintain satisfaction throughout, and regular meetings to align on progress and staging, with works executed to a high standard to prevent disruption to the operating tenant and limit downtime to an absolute minimum.